Project Duration
Stipulated Date of Commencement April 23 2014
Stipulated Date of Completion /
Likely Date of Completion
June 06 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 4,999,658.00
Awarded for ₹ 4,999,658.00

Project highlights

Repair/Upgrdation works of schools which includes roofing ,tiling,dadoes,painting etc.

 
Gallery Image
Contractors
M/s.S M Realtors
Gallery Image
Consultants
M/s.Creative Abode
 
Similar Projects

See Similar Projects

Similar Project

Repairs / Upgradation & Maintenance of Government High Schools in the State of Goa – GHS Netravali

View Project
Similar Project

Supply & Fixing of Ceramic Green Chalk Boards for Government Schools/ Colleges in the state of Goa

View Project
Similar Project

Repairs/Upgradation & Maintenance of Government Primary Schools in the State of Goa – Quepem Taluka- Package E

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.