Project Duration
Stipulated Date of Commencement
January 16 2019
Stipulated Date of Completion /
Likely Date of Completion January 30 2020
Likely Date of Completion January 30 2020
Status
100%
Completed
Cost (₹)
Estimated at
₹ 12,461,292.00
Awarded for
₹ 13,923,377.44
Project highlights
Repair/Upgrdation works of schools which includes roofing ,tiling,dadoes,painting etc.
Contractors
M/s. Rahul Constructions
Consultants
M/s. Nitin Arolkar
See Similar Projects
Repairs/Upgradation and Maintenance of Govt. schools in the state of Goa – Civil, Plumbing and Electrical works-Bicholim Taluka- Package C (G.P.S Gaokarwada Mayem, G.P.S Shirodawadi Mulgao, G.P.S. Haturli Mayem)
View Project
Repairs/Upgradation & Maintenance of Government schools in the State of Goa – CIVIL PLUMBING & ELECTRICAL WORKS works-Bicholim Taluka – Package L (GPS Tale Pale & GPS Ghongree Maina Navelim)
View Project
Reconstruction of Government Primary School at Arla Querim – Civil, Plumbing and Electrical Works
View Project