Project Duration
Stipulated Date of Commencement
June 22 2015
Stipulated Date of Completion /
Likely Date of Completion October 21 2015
Likely Date of Completion October 21 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 4,988,924.00
Awarded for
₹ 4,988,924.00
Project highlights
Repair/Upgrdation works of schools which includes roofing , tiling,dadoes,painting etc.
Contractors
M/s.Duracore Constructions
Consultants
M/s.Nitin Arolkar