Project Duration
Stipulated Date of Commencement
February 01 2017
Stipulated Date of Completion /
Likely Date of Completion January 01 2018
Likely Date of Completion January 01 2018
Status
100%
Completed
Cost (₹)
Estimated at
₹ 45,782,655.00
Awarded for
₹ 47,540,516.74
Project highlights
Repair/Upgrdation works of schools which includes roofing ,tiling,dadoes,painting etc.
Contractors
M/s.K G Thomas
Consultants
M/s.Manoj Amshekar