Project Duration
Stipulated Date of Commencement
February 14 2019
Stipulated Date of Completion /
Likely Date of Completion August 28 2019
Likely Date of Completion August 28 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 5,765,344.00
Awarded for
₹ 6,453,546.81
Project highlights
Repairs/Upgradation and maintenance of Government schools in the state of Goa – Sattari Taluka
Contractors
M/s. MAI-TAT Associates
Consultants
M/s. Bhaskar Wagle and Associates
See Similar Projects
Repairs/Upgradation and Maintenance of Government Schools in the state of Goa-Mormugao Taluka-Package C (GPS Cansaulim, GPS Podxiro, GPS Chicalim, GPMS Cortalim)
View Project
Upgradation/ Renovation of Goverrnent College of Art , Science and Commerce , Sanquelim- Goa – Additional Work-I – Furniture Works
View Project
Repairs/Upgradation and Maintenance of Govt. schools in the state of Goa – Civil, Plumbing and Electrical works-Bicholim Taluka – Package H (G.P.S Kharekhajan- Virdi, G.P.S Kudchire, G.P.S. Pratap Nagar- Harvalem, G.H.S. Late Jayendra J. Rane- Kudchire)
View Project