Project Duration
Stipulated Date of Commencement
December 25 2016
Stipulated Date of Completion /
Likely Date of Completion September 24 2017
Likely Date of Completion September 24 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 43,479,284.00
Awarded for
₹ 44,372,186.00
Project highlights
football ground of size 77.65m x 62.00m with 3.00 mts. warm up area all around the ground with 850 spectator stand capacity. Provision of basket ball court and vollyball court. Also consist of G+1 club house.
Contractors
M/s. Indage Development Construction Pvt. Ltd.
Consultants
M/s. Gurudutt Sanzgiri
See Similar Projects
Repairs/Upgradation and maintenance of Government schools in the state of Goa –Package B (Salcete Taluka) – (GPS Baradi, GPS Chandor, GMS Sao Jose de Areal, GPS Gudi Paroda) – 4th call
View Project
Repairs / Upgradation & Maintenance of Government High Schools in the State of Goa – GHS Netravali
View Project
Upgradation/Renovation of Government College at Quepem, Goa -Civil, Plumbing, Acoustic, Electrical, HVAC and Fire Fighting work.
View Project