Project Duration
Stipulated Date of Commencement
February 28 2015
Stipulated Date of Completion /
Likely Date of Completion August 27 2015
Likely Date of Completion August 27 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 40,000,000.00
Awarded for
₹ 40,000,000.00
Project highlights
Repairs/ Upgradation & Maintenance of schools
Contractors
M/s. Duracore Constructions
Consultants
M/s. Nitin Arolkar
See Similar Projects
Repairs/Upgradation & maintenance of Government schools in the state of Goa – Civil, Plumbing & Electrical works- Package-IV (Sattari Taluka )
View Project
Construction of Compound Wall for Ashram school under centrally sponsored scheme of Ministry of Tribal Affairs at “MOSHIPHOND” in the Land under Survey no. 20/0 in the Village Poinguinim of Canacona Taluka.
View Project
Construction of Concrete Road for Ashram school under centrally sponsored scheme of Ministry of Tribal Affairs at “MOSHIPHOND” in the Land under Survey no. 20/0 in the Village Poinguinim of Canacona Taluka.
View Project