Project Duration
Stipulated Date of Commencement
September 30 2018
Stipulated Date of Completion /
Likely Date of Completion May 29 2019
Likely Date of Completion May 29 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 7,363,633.61
Awarded for
₹ 8,266,757.43
Project highlights
Repairs/ Upgradation & Maintenance of Government Primary school building
Contractors
M/s. Shrusti construction
Consultants
M/s. Playgroup studio