Project Duration
Stipulated Date of Commencement
February 01 2017
Actual Date of Completion
May 23 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 45,782,655.00
Awarded for
₹ 47,540,516.74
Final Cost of Project
₹ 33976494
Project highlights
Repair/Upgrdation works of schools which includes roofing ,tiling,dadoes,painting etc.
Contractors
M/s K G Thomas
Consultants
M/s Manoj Amshekar