Project Duration
Stipulated Date of Commencement
December 18 2018
Stipulated Date of Completion /
Likely Date of Completion June 30 2019
Likely Date of Completion June 30 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 8,824,012.00
Awarded for
₹ 9,870,545.33
Project highlights
Repairs/Upgradation & Maintenance of Government Schools
Contractors
M/s. Sirajuddin beig
Consultants
M/s. Bhaskar Wagle & Associates