Project Duration
Stipulated Date of Commencement
February 03 2014
Actual Date of Completion
November 30 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 249,720,042.00
Awarded for
₹ 262,072,165.00
Final Cost of Project
₹ 329,762,462.00
Project highlights
Projects include construction of New Arts block Commerce block , Library, and Mutipurpose Hall and renovation of existing block.
Contractors
M/s. Harsh Construction Pvt. Ltd.
Consultants
M/s. Effective Architectural Services