Project Duration
Stipulated Date of Commencement February 03 2014
Actual Date of Completion November 30 2019
Status
100%
Completed
Cost (₹)
Estimated at ₹ 249,720,042.00
Awarded for ₹ 262,072,165.00
Final Cost of Project ₹ 329,762,462.00

Project highlights

Projects include construction of New Arts block Commerce block , Library, and Mutipurpose Hall and renovation of existing block.

 
Contractors
M/s. Harsh Construction Pvt. Ltd.
Consultants
M/s. Effective Architectural Services
 