Project Duration
Stipulated Date of Commencement
November 14 2019
Stipulated Date of Completion /
Likely Date of Completion April 22 2020
Likely Date of Completion April 22 2020
Status
100%
Completed
Cost (₹)
Estimated at
₹ 4,867,479.00
Awarded for
₹ 4,791,813.70
Project highlights
Repairs/Upgradation of School
Contractors
M/s. Sushant Khedekar
Consultants
M/s. Creative Abode.