Project Duration
Stipulated Date of Commencement
June 22 2015
Stipulated Date of Completion /
Likely Date of Completion October 21 2015
Likely Date of Completion October 21 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 3,976,710.00
Awarded for
₹ 3,976,710.00
Project highlights
Repair/Upgrdation works of schools which includes roofing , tiling,dadoes,painting etc.
Contractors
M/s.Duracore Constructions
Consultants
M/s.Nitin Arolkar
See Similar Projects
Repairs/Upgradation and maintenance of Govt. schools in the State of Goa-Civil, Plumbing and Electrical works -Salcete Taluka-Package B (GPS Baradi, GPS Chandor, GMS Sao Jose de Areal, GPS Gudi Paroda)-4th CALL.
View Project
Construction of Anganwadi Centres from NABARD Assistance – Package IV (GPS Chandel, GPS Ibrampur, GPS Hansapur).
View Project
Supply & Installation of Furniture for Government Schools and Colleges in the State of Goa
View Project





