Project Duration
Stipulated Date of Commencement May 02 2015
Actual Date of Completion April 30 2016
Status
100%
Completed
Cost (₹)
Estimated at ₹ 1,325,881.00
Awarded for ₹ 1,127,228.50
Final Cost of Project ₹ 1,761,777.00
 
Contractors
M/s. Vrindavan Agricultural Services
Consultants
M/s. Effective Architectural Services
 