Project Duration
Stipulated Date of Commencement July 28 2011
Actual Date of Completion April 27 2016
Status
100%
Completed
Cost (₹)
Estimated at ₹ 18,868,930.00
Awarded for ₹ 18,856,723.50
Final Cost of Project ₹ 38,878,981.00
 
Contractors
M/s Shree Manguirish Air Conditioning Company
Consultants
M/s. Effective Architectural Services
 

See Similar Projects

Power upgradation works (Phase I) for GMC Complex and Nurses’ College Campus, Bambolim, Goa.

View Project

Providing interiors to office premises of Commercial Tax Department at Ponda.

View Project

Upgradation of Hospital facilities at Goa Medical College, Bambolim, Hospicio Hospital at Margao and RMD at Thane & Keri. SH- Upgradation of Ward Nos. 120, 123, 124, staff rest rooms and other miscellaneous works at Goa Medical College and Hospital at Bambolim, Goa-Extension of Ward 125 for Cardiology Department at Goa Medical College, Bambolim-Goa.