Project Duration
Stipulated Date of Commencement January 17 2014
Stipulated Date of Completion /
Likely Date of Completion
March 17 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 975,000.00
Awarded for ₹ 970,000.00
 
Gallery Image
Contractors
M/S. ENCARTA PHARMA PVT. LTD
Gallery Image
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Road works (concrete and paver) and landscaping works

View Project
Similar Project

Construction of Sewage Treatment Plant and Elevated tank platform.

View Project
Similar Project

Maintenance works at Goa Medical College and Hospital S.H.: Maintenance Contract for Dubas make online UPS Systems and Servo Stabilizers installed in GMC Hospital Complex Bambolim forsix months.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.