Project Duration
Stipulated Date of Commencement February 08 2015
Actual Date of Completion April 27 2016
Status
100%
Completed
Cost (₹)
Estimated at ₹ 1,507,609.00
Awarded for ₹ 1,571,883.00
Final Cost of Project ₹ 1,425,287.00
 
Contractors
M/s. Goa Friend’s Engineering & Electricals Pvt. Ltd
Consultants
M/s. Effective Architectural Services
 