Project Duration
Stipulated Date of Commencement
November 03 2014
Actual Date of Completion
December 10 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 5,004,199.48
Awarded for
₹ 4,585,843.00
Final Cost of Project
₹ 5,133,459.00
Project highlights
The scope of work invloves supply of decorative street light poles at Mont Boa Vista at Old Goa
Contractors
M/s. James Electrical
Consultants
M/s. Prabhugaonker and Associates