Project Duration
Stipulated Date of Commencement January 25 2007
Stipulated Date of Completion /
Likely Date of Completion
November 24 2007
Status
100%
Completed
Cost (₹)
Estimated at ₹ 39,118,679.00
Awarded for ₹ 42,524,358.16

Project highlights

Demolition of old structures and construction of new RCC structure, supply & installation of c-tech machinery and upgradation of existing units.

 
Gallery Image
Contractors
M/s. Gharpure Engineering and Constructions Pvt. Ltd.
Gallery Image
Consultants
M/s. FP INDIA PROJECT MANAGEMENT CONSULTANCY SERVCIES PVT. LTD
 
Similar Projects

See Similar Projects

Similar Project

Supply Installation Testing & Commissioning of Bio Medical Equipment (Part III) CT Scan.

View Project
Similar Project

Upgradation of Hospicio Hospital at Margao.

View Project
Similar Project

Design, manufacture, supply, installation, testing, commissioning and maintenance of elevators

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.