Project Duration
Stipulated Date of Commencement
March 03 2007
Stipulated Date of Completion /
Likely Date of Completion April 02 2009
Likely Date of Completion April 02 2009
Status
100%
Completed
Cost (₹)
Estimated at
₹ 174,969,028.00
Awarded for
₹ 186,209,408.98
Project highlights
RCC five storeyed building.
Ground Floor : Casualty ward & morgue, O.T.
First Floor : Consulting rooms.
Second Floor : Surgical wards, OT (04 nos.), ICU.
Third Floor : Pediatric wards, gynecology wards, antenatal ward, post natal wards, OT, special & twin private rooms.
Fourth Floor : Medicine Ward (Male & Female), ICCU, Conference Room.
Contractors
M/s. IVRCL Infrastructure & Projects Ltd.
Consultants
M/s. Intertek Architects & Consultants Pvt. Ltd.
See Similar Projects
– Hospital Furniture
View Project
Civil & Plumbing works (Phase-II) – Balance works.
View Project
Renovation/Maintenance of Hospitals, CHCs, PHCs, RMDs under Directorate of Health Services in South Goa S.H.: Maintenance Contract for the UPS systems installed at Upgraded Cottage Hospital, Chicalim for a period of three years (2019-2022)
View Project