Project Duration
Stipulated Date of Commencement
September 30 2016
Stipulated Date of Completion /
Likely Date of Completion March 29 2017
Likely Date of Completion March 29 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 17,575,621.00
Awarded for
₹ 21,667,827.00
Project highlights
Repair & upgradation work of the staicase with tilling, painting, railing, landscaping and minor civil works
Contractors
M/s. Race Constructions
Consultants
M/s. LKS India Pvt Ltd.
See Similar Projects
Lift/ Elevator Work
View Project
Electrical work
View Project
Upgradation of Infrastructure in the rural areas under Deendayal Panchayat Raj Infrastructure Development (Golden Jubilee) Scheme , 2013 -Pernem Taluka : Construction of Panchayat Complex cum Multipurpose Hall at V. P. Querim – Tiracol
View Project