Project Duration
Stipulated Date of Commencement
January 15 2022
Stipulated Date of Completion /
Likely Date of Completion April 14 2022
Likely Date of Completion April 14 2022
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,21,63,584.00
Awarded for
₹ 1,15,42,715.00
Project highlights
Supply and installation of furniture work
Contractors
M/s. Amardeep Designers India Pvt. Ltd.
Consultants
M/s. Datta Kare Associates