Project Duration
Stipulated Date of Commencement
October 28 2016
Actual Date of Completion
Status
100%
Completed
Cost (₹)
Estimated at
₹ 9,721,364.00
Awarded for
₹ 11,039,275.00
Final Cost of Project
₹ 11,800,649.00
Project highlights
Repair & upgradation work of the school building, including roofing, painting, tilling, plumbing work etc
Contractors
M/s. Sirrajuddin Beig
Consultants
M/s. Nitin Arolkar
See Similar Projects
Upgradation of Ward Nos. 120, 123, 124, staff rest rooms and other miscellaneous works at Goa Medical College and Hospital at Bambolim, Goa : SH – Procurement of additional works/items and medical equipments required for Ward No.125 and Cardiovascular Surgical Operation Theatre- Supply, Installation and Testing and Commissioning of Xenon Headlight