Project Duration
Stipulated Date of Commencement September 01 2015
Actual Date of Completion June 22 2016
Status
100%
Completed
Cost (₹)
Estimated at ₹ 482,628.00
Awarded for ₹ 446,140.00
Final Cost of Project ₹ 490,753.50
 
Contractors
M/s. Karant Electricals
Consultants
M/s. Saolapurkar and Associates
 