Project Duration
Stipulated Date of Commencement
November 11 2017
Stipulated Date of Completion /
Likely Date of Completion October 12 2017
Likely Date of Completion October 12 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 18,680,476.00
Awarded for
₹ 15,562,927.50
Project highlights
Resurfacing of roads in Panaji city for IFFI 2017
Contractors
M/s.Assmas Constructions Pvt. LTd
Consultants
M/s.Vaishali Pednekar & Associates