Project Duration
Stipulated Date of Commencement
July 09 2012
Actual Date of Completion
May 27 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 4,28,94,732.00
Awarded for
₹ 37,798,417.00
Final Cost of Project
₹ 38,472,730.00
Contractors
M/s. Durian Industries Ltd.
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.