Project Duration
Stipulated Date of Commencement
November 14 2017
Actual Date of Completion
December 20 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 12,019,832.00
Awarded for
₹ 8,371,107.76
Final Cost of Project
₹ 7,832,764.00
Project highlights
Painting of buildings for IFFI 2017
Contractors
M/s Rakesh Kambli
Consultants
M/s Vaishali Pednekar & Associates