Project Duration
Stipulated Date of Commencement June 16 2013
Stipulated Date of Completion /
Likely Date of Completion
June 15 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 20,000,000.00
Awarded for ₹ Rate contract

Project highlights

Maintenance works at Goa Medical College and Hospital & Goa Dental College at Bambolim, Goa

 
Gallery Image
Contractors
M/s. Deshpande Constructions
Gallery Image
Consultants
M/s. Frishmann Prabhu (I) Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Air Conditioning work

View Project
Similar Project

Road works (concrete and paver) and landscaping works

View Project
Similar Project

Design, supply, erection, testing and commissioning of 5 Nos. pre-fabricated Modular Operation Theatres along with centralised medical gas pipe system within the 5 No. OTs at Goa Medical College & Hospital, Bambolim, Goa

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.