Project Duration
Stipulated Date of Commencement
July 07 2013
Actual Date of Completion
August 31 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 19,12,103.00
Awarded for
₹ 21,94,753.54
Final Cost of Project
₹ 2327969
Project highlights
Premonsoon works
Contractors
M/s. Deshpande Constructions,
Consultants
M/s. Frishmann Prabhu (I) Pvt. Ltd.,