Project Duration
Stipulated Date of Commencement December 23 2005
Actual Date of Completion February 12 2006
Status
100%
Completed
Cost (₹)
Estimated at ₹ 526,300.00
Awarded for ₹ 678,618.00
Final Cost of Project ₹ 632,698.00

Project highlights

The work includes external electrical works

 
Contractors
M/s. Ohm Engineers, M/s. Ohm Engineers
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd
 