Project Duration
Stipulated Date of Commencement
December 23 2005
Stipulated Date of Completion /
Likely Date of Completion February 10 2006
Likely Date of Completion February 10 2006
Status
100%
Completed
Cost (₹)
Estimated at
₹ 526,300.00
Awarded for
₹ 678,618.00
Project highlights
The work includes external electrical works
Contractors
M/s. Ohm Engineers
Consultants
M/s. FP INDIA PROJECT MANAGEMENT CONSULTANCY SERVCIES PVT. LTD
See Similar Projects
Central Sterile Supply Department.
View Project
Interior Works
View Project
Upgradation of Cansaulim Primary Health Centre (PHC) in Cortalim Constituency
View Project