Project Duration
Stipulated Date of Commencement December 23 2005
Stipulated Date of Completion /
Likely Date of Completion
February 10 2006
Status
100%
Completed
Cost (₹)
Estimated at ₹ 526,300.00
Awarded for ₹ 678,618.00

Project highlights

The work includes external electrical works

 
Gallery Image
Contractors
M/s. Ohm Engineers
Gallery Image
Consultants
M/s. FP INDIA PROJECT MANAGEMENT CONSULTANCY SERVCIES PVT. LTD
 
Similar Projects

See Similar Projects

Similar Project

Supply, installation, testing and commissioning of Air Conditioners and ventilation system

View Project
Similar Project

Civil, Plumbing, Electrical, Lift & Fire – Fighting works – Balance works

View Project
Similar Project

Supply, Installation, Testing and Commissioning of Central Sterile Services Department(CSSD) Equipments

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.