Project Duration
Stipulated Date of Commencement
December 23 2005
Actual Date of Completion
February 12 2006
Status
100%
Completed
Cost (₹)
Estimated at
₹ 526,300.00
Awarded for
₹ 678,618.00
Final Cost of Project
₹ 632,698.00
Project highlights
The work includes external electrical works
Contractors
M/s. Ohm Engineers, M/s. Ohm Engineers
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd