Project Duration
Stipulated Date of Commencement
October 26 2020
Stipulated Date of Completion /
Likely Date of Completion December 31 2023
Likely Date of Completion December 31 2023
Status
100%
Completed
Cost (₹)
Estimated at
₹ 6,851,435.00
Awarded for
₹ 4,998,675.00
Project highlights
Maintenance Work
Contractors
M/s. Vigneshwar Air Conditioning Pvt. Ltd
Consultants
In-house (GSIDC)
See Similar Projects
Procurement of Equipment for Burns unit (New Ward 118) Dept. of Plastic Surgery, GMC, Bambolim Goa – SH: SITC of Flash Autoclave
View Project
Hospital furniture work.
View Project
SITC of medical gas supply system (MGSS)
View Project





