Project Duration
Stipulated Date of Commencement November 06 2008
Actual Date of Completion June 09 2011
Status
100%
Completed
Cost (₹)
Estimated at ₹ 3,150,000.00
Awarded for ₹ 3,560,000.00
 
Contractors
M/s. Thyssenkrup Electrical (I) Ltd.
Consultants
M/s.Architecture Autonomous PMC with Frischmann Prabhu India (I) Pvt Ltd.
 