Project Duration
Stipulated Date of Commencement March 05 2014
Stipulated Date of Completion /
Likely Date of Completion
August 04 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 21,102,630.00
Awarded for ₹ 22,784,504.40

Project highlights

Maintenance of bridges (South Goa)

 
Gallery Image
Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd.,
Gallery Image
Consultants
Pre tender – M/s. Kashec Engineers Pvt. Ltd., Post tender In-house (GSIDC)
 
Similar Projects

See Similar Projects

Similar Project

Landscaping work.

View Project
Similar Project

Supply of Poles And Light Fixtures

View Project
Similar Project

Construction of Bus Stand at Shiroda – Phase I : Land Development

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.