Project Duration
Stipulated Date of Commencement
July 16 2010
Stipulated Date of Completion /
Likely Date of Completion October 15 2010
Likely Date of Completion October 15 2010
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,985,905.00
Awarded for
₹ 2,183,970.00
Contractors
M/s. Deshpande Constructions
Consultants
M/s. Vijaykumar Sawant Associates