Project Duration
Stipulated Date of Commencement
April 28 2010
Actual Date of Completion
June 30 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 174,633,507.09
Awarded for
₹ 185,911,708.00
Final Cost of Project
₹ 206,789,283.00
Project highlights
Bridge across tributary of river Chapora connecting villages Ozari and Tharmas.
Contractors
M/s. Aditya Construction Co., M/s. Aditya Construction Co.
Consultants
M/s. Mahimtura Consultants Pvt. Ltd., M/s. Mahimtura Consultants Pvt. Ltd.