Project Duration
Stipulated Date of Commencement
June 26 2009
Stipulated Date of Completion /
Likely Date of Completion January 25 2010
Likely Date of Completion January 25 2010
Status
100%
Completed
Cost (₹)
Estimated at
₹ 50,52,760.00
Awarded for
₹ 5,122,999.00
Contractors
M/s. Mohan Electricals
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.
See Similar Projects
Renovations of old IPHB Building to accommodate Nursing Hostel and College and Directorate of Food & Drugs
View Project
Fire fighting work.
View Project
Air Conditioning and Ventilation System
View Project





