Project Duration
Stipulated Date of Commencement November 16 2007
Actual Date of Completion May 15 2008
Status
100%
Completed
Cost (₹)
Estimated at ₹ 14,588,059.00
Awarded for ₹ 13,938,532.61
Final Cost of Project ₹ 12,448,983.87

Project highlights

Interior works, like false ceiling, providing of loose furnitures, signages etc.

 
Contractors
M/s. Idea Incorporation
Consultants
M/s. M. S. Suctancar
 