Project Duration
Stipulated Date of Commencement
March 02 2014
Stipulated Date of Completion /
Likely Date of Completion April 16 2014
Likely Date of Completion April 16 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,863,663.00
Awarded for
₹ 2,749,999.50
Project highlights
HVAC work
Contractors
M/s. Vighneshwar Air Conditioning Pvt. Ltd.
Consultants
M/s. KICONS Pvt. Ltd.