Project Duration
Stipulated Date of Commencement
March 12 2007
Stipulated Date of Completion /
Likely Date of Completion July 12 2007
Likely Date of Completion July 12 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,844,298.00
Awarded for
₹ 4,007,820.80
Project highlights
Development of plots under 20 point programme scheme at Podocem.
Contractors
M/s. Assmas Constructions Pvt. Ltd.
Consultants
In-house (GSIDC)