Project Duration
Stipulated Date of Commencement June 13 2016
Stipulated Date of Completion /
Likely Date of Completion
July 07 2016
Status
100%
Completed
Cost (₹)
Estimated at ₹ 2,405,439.00
Awarded for ₹ 2,390,319.50

Project highlights

Air conditioning work

 
Gallery Image
Contractors
M/s. Shree Manguirish Airconditioning Co
Gallery Image
Consultants
M/s. Archivista Engineering Projects. Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Construction of Government Primary School at Guddemol, Sanguem, Goa.

View Project
Similar Project

Repairs/ Upgradation & Maintenance of Government schools in the State of Goa –Civil, Plumbing & Electrical works in Bardez Taluka :- GPS Betim, GPS Salvaor do Mund, GPS Paithona

View Project
Similar Project

Demolition of Hostel building (front side) at Inspectorate of Factories & Boilers.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.