Project Duration
Stipulated Date of Commencement
February 13 2019
Actual Date of Completion
November 30 2020
Status
100%
Completed
Cost (₹)
Estimated at
₹ 6,426,497.00
Awarded for
₹ 7,911,250.50
Final Cost of Project
₹ 5,390,160.00
Project highlights
Repairs of Govt. Schools in Pernem Taluka – Civil, Plumbing, Electrical works
Contractors
M/s. Sunil Enterprises
Consultants
M/s. Oracle Structural Consultants