Project Duration
Stipulated Date of Commencement
February 12 2009
Actual Date of Completion
June 07 2009
Status
100%
Completed
Cost (₹)
Estimated at
₹ 50,71,379.00
Awarded for
₹ 47,00,750.52
Contractors
M/s. Rohit Equipments
Consultants
M/s. Datta Kare Associates