Project Duration
Stipulated Date of Commencement February 12 2009
Actual Date of Completion June 07 2009
Status
100%
Completed
Cost (₹)
Estimated at ₹ 50,71,379.00
Awarded for ₹ 47,00,750.52
 
Contractors
M/s. Rohit Equipments
Consultants
M/s. Datta Kare Associates
 