Project Duration
Stipulated Date of Commencement July 19 2008
Actual Date of Completion December 30 2009
Status
100%
Completed
Cost (₹)
Estimated at ₹ 37,765,721.00
Awarded for ₹ 49,674,821.00
Final Cost of Project ₹ 48,072,689.00

Project highlights

The Panchayat Ghar and Football ground is housed on net area of 10,225 sq.m.The building is Ground + 2 having total covered area on the ground floor of 875 sq.m., first floor 761.74 sq.m., second floor 807.10sq. m.• Ground floor will house Bank, Health Centre, Balwadi, and Recreation Area with toilets, Change Room with Wash Room for football players, Room for Electricity Department, separate toilets for gents and ladies.• First floor will house Panchayat Office, Gram Sabha Hall, and 3 Cabins each for Secretary, Sarpanch, Talathi and Library, Games Room, Gymnasium with Wash Room, Separate toilets for gents and ladies.• Second Floor will house main Community Hall with stage, Dining Hall, Green Room, toilets facilities for gents and ladies.• Lift with provision for 8 persons.• The football ground is 90 x 60 pitch with natural turf and having a sprinkler system with well for irrigation.

 
Contractors
M/s. Ruby Realtors Pvt. Ltd.
Consultants
M/s. Datta Kare Associates
 

See Similar Projects

Infrastructure Works for Sanjay Centre for Special Education At Porvorim – HVAC work

View Project

Construction of Government Primary School at Guddemol, Sanguem, Goa.

View Project

Reconstruction of school at GPS Bicholim (Central)

View Project
x