Project Duration
Stipulated Date of Commencement
July 26 2016
Stipulated Date of Completion /
Likely Date of Completion September 08 2016
Likely Date of Completion September 08 2016
Status
100%
Completed
Cost (₹)
Estimated at
₹ 999,534.00
Awarded for
₹ 1,044,450.00
Project highlights
The scope of work includes supply, installation, testing & commissioning of :
a) 160kVA,11/.415kV Distribution transformer
b) 11kV Load Break Switch
c) HT Metering cubicle and other allied electrical works.
Contractors
M/s. Aditya Electromech Services
Consultants
M/s. Archivista Engineering Projects. Pvt. Ltd.
See Similar Projects
Repairs/Upgradation & Maintenance of Govt. Schools in the State of Goa – (Ponda Taluka) – (GPS Dharzo,GPS Gaune No 2 , GPS Gauthan Priol, GPS Hanso & GPS Parampai )
View Project
Infrastructure Works For Sanjay Centre For Special Education at Bogda, Vasco -SH:Fire safety and exit signages work
View Project
Construction of Government High School at Bhuipal in Sattari Taluka.
View Project