Project Duration
Stipulated Date of Commencement
September 01 2006
Actual Date of Completion
October 03 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 5,881,225.00
Awarded for
₹ 6,030,626.00
Final Cost of Project
₹ 6,355,893.00
Contractors
M/s. Mahabaleshwar Construction Company, M/s. Mahabaleshwar Construction Company
Consultants
M/s. Effective Architectural Services, M/s. Effective Architectural Services