Project Duration
Stipulated Date of Commencement
January 01 2011
Stipulated Date of Completion /
Likely Date of Completion March 31 2011
Likely Date of Completion March 31 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 6,21,50,944.00
Awarded for
₹ 6,35,16,466.50
Contractors
M/s. Assmas Constructions Pvt. Ltd.
Consultants
M/s. Construma Consultancy Pvt. Ltd.