Project Duration
Stipulated Date of Commencement
November 10 2018
Stipulated Date of Completion /
Likely Date of Completion March 09 2019
Likely Date of Completion March 09 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 16,502,837.00
Awarded for
₹ 15,742,876.00
Project highlights
alteration to the interiors of the existing science block and other miscellaneous works
Contractors
M/s. Deshpande Constructions
Consultants
M/s. Kicons Limited