Project Duration
Stipulated Date of Commencement
September 14 2018
Actual Date of Completion
July 01 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 775,410.00
Awarded for
₹ 719,999.00
Final Cost of Project
₹ 719,999.00
Project highlights
SITC of 11KV 4 Way outdoor type RMU and other allied works at R.M.O Hostel at Goa Medical College.
Contractors
M/s. Volton Engineering (I) Pvt. Ltd.,
Consultants
M/s. Frishmann Prabhu (I) Pvt. Ltd.