Project Duration
Stipulated Date of Commencement
September 14 2018
Stipulated Date of Completion /
Likely Date of Completion November 13 2018
Likely Date of Completion November 13 2018
Status
100%
Completed
Cost (₹)
Estimated at
₹ 775,410.00
Awarded for
₹ 719,999.00
Project highlights
SITC of 11KV 4 Way outdoor type RMU and other allied works at R.M.O Hostel at Goa Medical College.
Contractors
M/s. Volton Engineering (I) Pvt. Ltd.,
Consultants
M/s. Frishmann Prabhu (I) Pvt. Ltd.
See Similar Projects
Supply, installation, testing and commissioning of Central Air Conditioning System for GMC Complex at Bambolim, Goa.
View Project
Upgradation of Ward Nos.120, 123, 124, Staff Rest Rooms (Old Garage) and other miscellaneous works at Goa Medical College and Hospital at Bambolim, Goa
View Project
Construction of New Premises for Community Health Centre at Tuem, Pernem Goa and Major Civil works sanctioned under NRHM – ROP 2012-13.: Phase I: Repair and upgradation works of existing community health centre under NRHM
View Project