Project Duration
Stipulated Date of Commencement
February 02 2012
Stipulated Date of Completion /
Likely Date of Completion November 01 2012
Likely Date of Completion November 01 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 134,869,226.00
Awarded for
₹ 158,083,811.00
Project highlights
Development of temple premises.
Contractors
M/s. Indage Development Construction Pvt. Ltd.
Consultants
M/s. Effective Architectural Services (EAS