Project Duration
Stipulated Date of Commencement December 28 2023
Stipulated Date of Completion /
Likely Date of Completion
August 31 2024
Status
28%
Completed
Cost (₹)
Estimated at ₹ 21,307,622.00
Awarded for ₹ 22,871,315.00

Project highlights

Project includes development of work place at third floor, such as – interior and other allied works

 
Gallery Image
Contractors
M/s. Concept Creator
Gallery Image
Consultants
M/s. UCJ Architecture & Environment
 
Similar Projects

See Similar Projects

Similar Project

Redesigning and reconstruction of existing buildings and additional construction and new administration and training block for Fire station at Panaji,Goa.

View Project
Similar Project

Repairs/ Maintenance of Buildings under Directorate of Food and Drugs Administration, Bambolim – Goa. S.H. –Maintenance Contract for the 180kVA Diesel Generator set installed at Directorate of Food and Drugs Administration, Bambolim for three years (2021-2024)

View Project
Similar Project

Construction of New Hostel Block for Institute of Psychiatry & Human Behaviour

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
    Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.