Project Duration
Stipulated Date of Commencement December 28 2023
Stipulated Date of Completion /
Likely Date of Completion
August 31 2024
Status
28%
Completed
Cost (₹)
Estimated at ₹ 21,307,622.00
Awarded for ₹ 22,871,315.00

Project highlights

Project includes development of work place at third floor, such as – interior and other allied works

 
Gallery Image
Contractors
M/s. Concept Creator
Gallery Image
Consultants
M/s. UCJ Architecture & Environment
 
Similar Projects

See Similar Projects

Similar Project

Construction of Terminal Building for Captain of Ports at Panaji, Goa – HVAC Works

View Project
Similar Project

Protection & Restoration of Mandovi River Coastline from Miramar Circle to Youth Hostel and from Kala Academy to ESG

View Project
Similar Project

Maintenance works at Goa Medical College and Hospital S.H.: Maintenance Contract for the OTIS make 20 passenger cum bed lift installed at Plastic Surgery ward, Goa Medical College, Bambolim for a period of three years (2020-2023)

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.